In early 2023, Onyx completed a 1.6MW solar and 2.2MWh storage portfolio for the City of Downey in CA, a process which began with the City's selective RFP process in 2021.
Through a 25-year PPA, which includes all battery equipment and operating costs, Onyx will deliver Downey an estimated $10M in utility cost savings over the lifetime of the projects.
With energy production estimated at over 2.675MWh in year one, the City is expected to avoid utility costs upwards of $475k in its first year of solar + storage operation alone.
The clean energy solutions are estimated to offset ~90% of energy consumption at municipal facilities.
In addition to lower energy costs afforded by solar energy, Onyx's storage solutions will provide additional utility savings to Downey through program-automated peak demand shaving and time-of-use-related energy discharge incentives.
The battery storage will also provide the municipal facilities with energy resiliency against rolling power outages that CA typically experiences during high fire and wind seasons.
.
Currently, Onyx is equipping the City of Downey with solar and/or storage at six municipal locations through a combination of carport canopy and rooftop solutions: Downey City Hall, Police Department, Library & Theatre, Barbara J. Riley Senior Center, and Columbia Memorial Space Center.